A Survey Crew Is on Your Land, So Here Is Your Pipeline Playbook

When a company wants an easement for a pipeline or power line, the landowner who knows the process gets the better deal. Here are the steps.

You come home from town and there are orange flags in the back forty. Little ones, on wire stakes, marching across the pasture in a line as straight as a ruler. Nobody asked you. Nobody called. There is a white pickup at the fence line and a man in a reflective vest who is very polite and holds a clipboard and says, "Just doing some preliminary work, ma'am."

I want to be clear about something before we start. Pipelines and power lines are not the enemy. The country runs on them, and a lot of landowners have been treated fairly and paid well. But a company with a lawyer on every floor is about to sit across the table from you, and the single best predictor of a good deal is whether the landowner showed up prepared. This is the playbook. It is information, not legal advice, and the rules differ in every state, so you will need to check your own state's law.

Step 1: Understand who has the power to take your land, and why

The first thing to know is that some of these companies can condemn your land, which is the legal term for forcing a sale at a price a court sets. That is the power of eminent domain, and it comes from the same Fifth Amendment that requires "just compensation." (The story of how far that power can stretch is told in Kelo v. New London and the Backlash That Rewrote State Law.) Not every company has it, though.

  • Interstate natural gas pipelines. Under the Natural Gas Act of 1938, a company that holds a certificate of public convenience and necessity from the Federal Energy Regulatory Commission, or FERC, may use eminent domain to acquire the land it needs along the approved route, if it cannot reach an agreement with the owner. In 2021 the Supreme Court, in PennEast Pipeline Co. v. New Jersey, held that the grant extends even to land owned by a state.
  • Oil and other liquid pipelines. There is no general federal power of eminent domain for them. The authority, if any, comes from state law, and many states give it to pipelines that qualify as common carriers or public utilities. Some states are stricter than others.
  • Electric lines and local utilities. These usually get their power from state law and are overseen by a state public utility commission.

Ask the first question out loud: "Who are you, who regulates you, and what law gives you the right to enter my land?" A company that has a certificate will say so. A company that is only exploring routes may not have any condemnation power yet. Write down the answer.

Step 2: Read the survey notice

Many states let a company enter private land to survey a proposed route, usually after written notice and sometimes without the owner's consent. The rules vary: how many days' notice, what the crew may do, whether they must pay for damage. In some states a survey gives the company no right to build anything. It is a right to look.

Questions to ask in writing:

  1. Who is the company, and who is the project's owner behind it?
  2. What statute or permit authorizes the entry, and what is its date?
  3. How long will the crew be on the land, how many people, and what equipment?
  4. Will they dig, cut trees, drill soil borings or drive vehicles across crops?
  5. Who is responsible for damage to fences, crops, drain tile and livestock, and how will I be paid?
  6. Who is my contact person, and will they give me an actual name and phone number?

Do not sign a "right of entry" or "survey permission" form until you have read every line. Some of these forms quietly include terms beyond a simple survey, such as a right to construct or an agreement to negotiate only with one company. If you cannot tell what it does, do not sign until a lawyer has looked at it. You may also say no to a voluntary survey and make them follow the statutory process, which will require formal notice.

Step 3: Start a file

Before anything happens, document your land as it is now. Take dated photos and video of fields, fences, ponds, trees, gates and drainage. Collect these:

  • A map of your drain tile, if you have one. Tile is the most common casualty of pipeline construction, and it is expensive to fix.
  • Yield records for each field for several years.
  • Your property deed, survey and mortgage papers.
  • Any existing easements.
  • Your lender's name, since a mortgage lender may have to consent to a new easement.

If a dispute starts, the owner with a good file and a calm tone usually does better than the owner with a loud one.

Step 4: Learn the federal process if it is an interstate gas line

For an interstate natural gas pipeline, FERC runs a public process before it issues a certificate. There is a pre-filing stage, an environmental review and a comment period. Landowners can submit comments, and by following FERC's procedures and deadlines, you can intervene and become a formal party, which gives you a right to ask for rehearing and court review. The FERC website has a publication for landowners facing a gas pipeline, and it is worth reading in full. The deadlines are real, so mark your calendar when the notice arrives. (The paperwork side of the same maze is told in NEPA Explained, the 1970 Law Where Paperwork Outlasts the Project, and the story of what happens when a major pipeline gets tangled in the process is in From Application to Revocation, the Thirteen-Year Saga of Keystone XL.)

If the pipeline is not an interstate gas line, check your state's public utility or public service commission for the siting process and your rights to be heard.

Step 5: Negotiate the route first, then the money

Landowners often fight over price and forget to fight over the line on the map. Think about the route first. The question is not "should I oppose the project" but "where exactly does the easement cross my land, and what does it do to the way I farm?" A route down a fence line, along a property boundary or beside an existing easement can cost you much less than one that cuts a center-pivot field in half. Propose an alternative with a map. Companies do move routes, especially when you give them a workable option.

Then there is the easement itself. Ask for a draft in writing and look at:

  • Width. There is a permanent easement and a larger temporary construction easement. Know both.
  • Depth. Ask for a stated minimum depth of cover, so that plows and drain tile are not in danger. The number belongs in the contract, not in a verbal promise.
  • Allowed activities. What may you do on top of the line? Planting, grazing, crossing with equipment, building a fence, putting in a driveway?
  • Future lines. Does the company get to add more pipes in the same corridor without paying again? Many easement forms say so.
  • Assignment. Can the company sell the easement to someone else? Often it can, which means your counterparty can change.
  • Abandonment. What happens to the line when it is no longer used? Is it removed or left in the ground?
  • Indemnity. Who pays if the line leaks, explodes or injures somebody on your land? You want the company to pay, in writing.

Step 6: Count the money, not just the check

Compensation usually has several pieces, and each should be on its own line.

  1. The easement payment. The value of the land the company takes for the permanent right-of-way. In a condemnation case, the standard is fair market value, and a court may also compensate for the loss in value of the land you keep.
  2. Crop damage. For the crops lost during construction, and often for later years while the soil recovers.
  3. Restoration. Topsoil handling, compaction repair, fence and gate replacement, drainage repair and reseeding.
  4. Other damages. Livestock disruption, lost hay, lost timber, extra fencing, loss of access.

Here is a hypothetical, with round invented numbers. Say a company wants a construction right-of-way 100 feet wide across a field for one mile. A mile is 5,280 feet. So the construction strip is 5,280 times 100 = 528,000 square feet. An acre is 43,560 square feet, so that is 528,000 divided by 43,560, or about 12.1 acres. Call it 12 acres. If the field is in corn that makes 200 bushels an acre, and corn is worth $4.50 a bushel in this example, then each acre is worth 200 times $4.50 = $900. Twelve acres times $900 is $10,800 in the first year. Now suppose the compacted strip yields about 20 percent less in each of the next two years. That is 20 percent of $10,800 = $2,160 a year, or $4,320 for the two years. The total crop loss is $10,800 + $4,320 = $15,120.

Notice what that arithmetic shows. If the company offers one year of crop loss, $10,800, you are being offered less than three-quarters of the loss in this example. Many easement forms pay only the current crop, and that is a term worth negotiating. The numbers in your case will be different. The method is the same: acres, yield, price and years.

Step 7: Put the restoration promises in the contract

An oral promise from a land agent evaporates when the agent changes jobs. A written term survives. Ask for these in the easement or a side agreement:

  • Topsoil stripped and stored separately, then replaced in the right order.
  • Compaction ripping after construction.
  • Rock removal.
  • Drain tile repaired or replaced by a qualified contractor, with a warranty period.
  • Fences and gates repaired and livestock protected during construction.
  • A named company representative for complaints, and a method for disputes, such as independent monitoring paid for by the company.
  • A set timetable, and compensation for delays that push construction into your planting season.

Step 8: Know what happens if you cannot agree

If a company with condemnation power cannot get your signature, it can file a case in court. The court generally will not ask whether the project is a good idea, since the regulator has already decided that. The court decides how much compensation is due. In some interstate gas cases, courts have allowed the company to take possession early, before the amount is finally set, once the right to condemn is established. That is one reason not to ignore letters from the company's lawyers.

The practical lesson: negotiation is almost always stronger than a court battle, because you control more in negotiation. But the credible alternative of a hearing is what gives you leverage. A landowner who will walk into court with a good appraisal, a file and an attorney gets better offers than one who will not.

Step 9: When to call a lawyer

Call one as soon as you get a formal offer or a condemnation notice, before you sign anything. Look for a lawyer who handles easements and eminent domain for landowners, not for the companies. Ask whether the lawyer is paid by the hour or takes a percentage, and whether the company may be required to cover your costs. Many states allow a landowner to recover some legal costs in a condemnation case. Check yours. Also consider an independent appraiser who understands agricultural land.

A word on the bigger picture

I am not telling you to fight every project. America needs energy infrastructure, and in my view the answer to high energy bills is more production and more pipe, not less. If you want to see how the product you may be sitting on moves through the economy, Who Owns the Oil Under Your Farm, and Why America Answers Differently explains who owns the minerals, and Seven Fracking Horror Stories, Tested Against the Actual Record separates myth from record on the drilling that often fills the pipe. But conservative principle cuts both ways here. A free-market country honors private property, and a company that wants your land should treat you as a seller with rights, not as an obstacle. The rule is simple: if they want it, they pay for it. The property-rights law behind that is in The Takings Clause in Four Cases Every Landowner Should Know.

The bottom line

  • Slow down. A flag in your field is not a deadline. Do not sign anything the first day, and do not let a pleasant land agent rush you.
  • Find out whether the company can really condemn. An interstate gas pipeline with a FERC certificate can; others depend on your state's law.
  • Negotiate the route, the width and the depth before the price. The best deal is often the line that does the least harm to how you farm.
  • Count every dollar, including the second and third years. Crop loss, restoration, drainage and future lines all belong in the contract, in writing.
  • Call a landowner's lawyer early, and check your own state's law. An hour of advice before you sign is cheaper than a lifetime of regret.